Electricity Recovery Remains Low in Three Aceh Regencies

2 hours ago 10

December 30, 2025 | 08:46 pm

TEMPO.CO, Jakarta - Main Director of PT PLN (Persero) Darmawan Prasodjo said that the electricity recovery in three regencies in Aceh remains low. The mentioned areas are Central Aceh Regency, Bener Meriah Regency, and Gayo Lues Regency.

"For Central Aceh and Bener Meriah, our material evacuation is still conducted by air," he said in a joint meeting with the Indonesian Parliament, ministries, and institutions through a live YouTube broadcast on Tuesday, December 30, 2025.

Darmawan stated that the impact of the Sumatra floods on Aceh's electricity system is greater than the 2004 Aceh tsunami. At that time, there were 8 points of electrical system damage, while this time there are 442 points.

Darmawan said that 70.8 percent of villages in Central Aceh already have electricity, while the rest are still in the dark. In Bener Meriah, 80.41 percent of villages are already lit, and the rest are not. Then in Gayo Lues, 70 percent of villages are already lit, and the rest are not.

Darmawan mentioned that in Gayo Lues Regency, the route from Langsa to Kutacane to Blangkenjeren has started to open, so 210 PLN electric poles are on their way. "While for Aceh Tengah with Bener Meriah, the evacuation of 510 electric poles is still using Hercules aircraft," he said.

In addition to the electricity system, Darmawan said that although there are areas where recovery is fast, many homes of PLN customers are damaged. One example is in North Aceh Regency, where more than 80,000 homes are affected, with 13,000 units severely damaged, 20,000 units moderately damaged, and the rest slightly damaged.

Electricity repair in Aceh Utara is progressing quickly, but on the other hand, many residents' homes are damaged. In Aceh Tamiang, the evacuation route is running smoothly. Out of 209 villages, only seven are in the dark; the rest have light. "But the number of PLN customer homes affected is more than 38,000," he said.

Darmawan concluded that there are still other areas where electricity recovery is fast, but many PLN customer homes are also affected. This is influenced by the level of severity of the disaster that has occurred since the end of November.

Furthermore, in Bireun Regency, electricity has been restored to 607 out of 609 villages. Although only 2 villages are in the dark, more than 31,000 units are affected.

Then, in East Aceh Regency, 491 villages are already lit out of a total of 513 villages. The affected number is more than 11,000 homes.

In West Aceh Regency, there are 322 villages, and only 1 village that has not been lit again. "Here, the impact on homes is smaller than in others," said Darmawan.

Next, in Pidie Jaya Regency, Darmawan said, all 222 villages there have already regained electricity. However, more than 10,000 homes have been damaged, and some are still buried in mud.

Read: Aceh Tamiang Approves Land for 500 Flood Victims' Homes

Click here to get the latest news updates from Tempo on Google News



PLN Claims Aceh Power System Back to Normal After Floods

9 hari lalu

PLN Claims Aceh Power System Back to Normal After Floods

The President Director of PLN said they continue to accelerate the recovery of electricity after the Sumatra floods until the electricity network is fully restored to the public.


Nuclear Power Plant Homework

11 hari lalu

Nuclear Power Plant Homework

Indonesia is considering developing nuclear power plants in partnership with a Russian company. Institutional and safety preparedness is uncertain.


Electricity Returns to 5,961 of 6,500 Flood-Hit Villages in Aceh, ESDM Says

14 hari lalu

Electricity Returns to 5,961 of 6,500 Flood-Hit Villages in Aceh, ESDM Says

The ESDM Disaster Alert Team reports that electricity has been restored in 5,961 out of 6,500 villages affected by floods and landslides in Aceh.


PLN Reports 13 Power Component Thefts in Aceh

15 hari lalu

PLN Reports 13 Power Component Thefts in Aceh

PLN records at least 13 cases of electricity substation thefts since late November until December 14, 2025.


Over 1,200 Villages in Disaster-Hit Aceh Remain Without Electricity

21 hari lalu

Over 1,200 Villages in Disaster-Hit Aceh Remain Without Electricity

PLN targets several areas to have electricity gradually restored from December 11-31, 2025.


PLN: North Sumatra's Electricity Fully Restored After Floods and Landslides

22 hari lalu

PLN: North Sumatra's Electricity Fully Restored After Floods and Landslides

PLN has completed the entire process of restoring the electrical system affected by floods and landslides in North Sumatra.


BNPB Targets Full Electricity Restoration in Aceh by Monday Noon

22 hari lalu

BNPB Targets Full Electricity Restoration in Aceh by Monday Noon

Head of the National Disaster Management Agency (BNPB), Suharyanto, aims for 100% electricity recovery in Aceh by Monday, December 8, 2025.


Sumatra Floods: PLN Sends 250 kVA Generator to Central Aceh Hospital

23 hari lalu

Sumatra Floods: PLN Sends 250 kVA Generator to Central Aceh Hospital

The electricity system in Central Aceh has not been fully restored due to infrastructure damage caused by flash floods at the end of last November.


Power Supply in North Sumatra and Aceh Expected to Normalize by Saturday

25 hari lalu

Power Supply in North Sumatra and Aceh Expected to Normalize by Saturday

ESDM Minister Bahlil Lahadalia said power supply from Aceh to North Sumatra has begun to recover, although it has not yet returned to full capacity.


Regulation Revision Could Disrupt Energy Transition

27 hari lalu

Regulation Revision Could Disrupt Energy Transition

The Indonesian gov't is now revising Presidential Regulation No. 112/2022 on accelerating renewable energy development for electricity supply.


Read Entire Article
Pemilu | Tempo | |